swimming pool construction stages
NOTE : THE CIVIL DRAWING OF THE BASIN AND THE ELECTROMECHANICAL DRAWING OF THE CONNECTIONS MUST BE MADE FIRST.
1- REMOVAL AND DIGGING :
REMOVING EVERYTHING THAT HINDERS THE DIGGING PROCESS FROM WORKPLACE (CERAMIC, INTERLOCK, ETC... ) .
MAKE SURE THAT THE AREA IS FREE OF EXTENSIONS FIRST, IF YOU ARE NOT SURE, YOU MUST DIG MANUALLY.
2- HYGIENE WORK (PCC) :
THE GROUND MUST BE COMPACTED, AND MADE SURE OF ITS DURABILITY, AND ROADPIECE PLACED IF NECESSARY, THEN COVERED WITH NYLON.
THEN PUT THE REQUIRED CONCRETE, THICKNESS 5CM OR MORE.
3- BASIN BUILDING :
BUILD THE WALLS WITH BRICKS & CEMENT MIXTURE ACCORDING TO THE CIVIL DRAWING.
4- INITIAL ISOLATION :
DYEING THE FLOOR & WALLS WITH BITUMEN, THEN installing membrane sheets (bitumen rolls).
6- INTERNAL CONNECTIONS :
supplying the required pipes and power lines and placing them according to the electromechanical drawing.
7- Concrete ( shotcrete ) :
supplying ready-MIX Concrete according TO THE required specifications and placing it according to the civil drawing by a specialized team.
8- PLASTER :
( for edges, walls & floor ) .
5- MESH STEEL INSTALLATION :
supplying the required iron and placing it according to the civil drawing.
9- SECONDARY INSULATION :
making a cementation layer for the basin.
10- INSTALLATION THE EDGES.
11- INSTALLING CERAMICS :
GLUE and GROUT MUST BE SPECIAL FOR SWIMMING POOLS.
12- CONNECTIONS BETWEEN THE BASIN & CONTROL ROOM :
After completing the connection, must be CHECKED IT TO confirmed ITS safe.
13- INSTALL THE EQUIPMENT :
SUPPLY a filter that MATCHES the size of the POOL, and pumps FIT the filter. SHOULD BE installED by plumber specializED in swimming pools
14- INSTALL THE WHITENESS FOR THE POOL .
15- TEST & RUNNING :
MAKE SURE THE ALL VALVES ITS OPEN BEFORE FILLING THE WATER.