swimming pool construction stages

NOTE : THE CIVIL DRAWING OF THE BASIN AND THE ELECTROMECHANICAL DRAWING OF THE CONNECTIONS MUST BE MADE FIRST.

1- REMOVAL AND DIGGING :

  • REMOVING EVERYTHING THAT HINDERS THE DIGGING PROCESS FROM WORKPLACE (CERAMIC, INTERLOCK, ETC... ) .

  • MAKE SURE THAT THE AREA IS FREE OF EXTENSIONS FIRST, IF YOU ARE NOT SURE, YOU MUST DIG MANUALLY.

2- HYGIENE WORK (PCC) :

  • THE GROUND MUST BE COMPACTED, AND MADE SURE OF ITS DURABILITY, AND ROADPIECE PLACED IF NECESSARY, THEN COVERED WITH NYLON.

  • THEN PUT THE REQUIRED CONCRETE, THICKNESS 5CM OR MORE.

3- BASIN BUILDING :

  • BUILD THE WALLS WITH BRICKS & CEMENT MIXTURE ACCORDING TO THE CIVIL DRAWING.

4- INITIAL ISOLATION :

  • DYEING THE FLOOR & WALLS WITH BITUMEN, THEN installing membrane sheets (bitumen rolls).

6- INTERNAL CONNECTIONS :

  • supplying the required pipes and power lines and placing them according to the electromechanical drawing.

7- Concrete ( shotcrete )  :

  • supplying ready-MIX Concrete according TO THE required specifications and placing it according to the civil drawing by a specialized team.

8- PLASTER :

  • ( for edges, walls & floor ) .

5- MESH STEEL INSTALLATION  :

  • supplying the required iron and placing it according to the civil drawing.

9- SECONDARY INSULATION  :

  • making a cementation layer for the basin.

10- INSTALLATION THE EDGES.

11- INSTALLING CERAMICS :

  • GLUE and GROUT MUST BE SPECIAL FOR SWIMMING POOLS.

12- CONNECTIONS BETWEEN THE BASIN & CONTROL ROOM :

  • After completing the connection, must be CHECKED IT TO confirmed ITS safe.

13- INSTALL THE EQUIPMENT :

  • SUPPLY a filter that MATCHES the size of the POOL, and pumps FIT the filter. SHOULD BE installED by plumber specializED in swimming pools

14- INSTALL THE WHITENESS FOR THE POOL .

15- TEST & RUNNING :

  • MAKE SURE THE ALL VALVES ITS OPEN BEFORE FILLING THE WATER.